Level 2- Sprint 3- INV01 Inventory Ordering Module
Could someone please tell me what I am doing wrong with these formulas. @Misbah
1. Beginning Inventory =
IF 'SYS01 Time Settings By Week'.'1st Week of Timescale?' THEN 'DAT01 Beginning Inventory'.Beginning Inventory ELSE PREVIOUS(Ending Inventory)
2. Submit Purchase Order Request= OFFSET(PO Submitted, Shipping Time Weeks, 1) = 1
3. PO Submitted = IF Submit Purchase Order Request THEN 1 ELSE 0
4. Confirmed PO Delivery= IF PO Submitted > 0 THEN OFFSET(PO Submitted, Final Shipping Time Weeks, -1) ELSE 0
5. Confirmed Purchase Order Receipt= IF Confirmed PO Delivery > 0 THEN OFFSET(Final Shipment Amount, -Final Shipping Time Weeks, 0) ELSE 0
6.Shipping Time Weeks= 'TRA01 Shipping Metrics by Week'.'Shipping Time (Weeks)'[LOOKUP: 'SYS08 SKU Details'.Product]
Comments
-
I have tried everyting for this POST, OFFSET no matter what I try I do not get the desired result
0 -
@Misbah firstly thanks for all the comments you have put on various subjects - it is very helpful especially for level 2 when one is trying to learn independently
With respect to this discussion: Confirm Purchase Order Receipt I thought the guidance notes provides the answer:
- IF Confirmed PO Delivery > 0 THEN OFFSET(Suggested Order Amount for the Month, -Shipping Time Weeks, 0) ELSE 0
or have I misunderstood this? Or is this as an update?
Additionally for "Confirmed PO Delivery" you have recommeded POST - which I have tried and it works but the guidance is specifically asking to use OFFSET
"Set the Confirmed PO Delivery line item to use the PO Submitted 1 value and OFFSET it based on the number of weeks between the order and delivery.
- For example, if a PO Submitted has a value in Week 1 and the Shipping Time Weeks has a value of 2, there would be a value of 1 in the Confirmed PO Delivery line item in Week 3.
- Use the OFFSET function and reference the Shipping Time Weeks line items (should pull the value from the periods prior)."
If I use POST would that work for the exam?
0 -
Hi,
I have an issue on this step some of my lines are not charging the data so perhaps something is wrong ?
Such as the override amount and I dont understand why ?
0 -
I am unable to clear the Level 2 - Sprint 3 - Exam - I am getting maximum 60% only that New York question says incorrect answer and Other formulas also not able to figure out. Please help.
0
Categories
- All Categories
- 2.3K Anaplan Community
- Academy
- Anaplan Talent Builder
- Model Design Course
- The Anaplan Way
- Archive
- 2 Idea exchange
- 62 Enterprise Scale
- 1.1K Extensibility
- 21 Intelligence
- 1.6K Planning & Modeling
- 331 Security
- Community Connections
- Connections
- Experiences
- Groups
- Personas
- Employees
- CS Toolkit
- Customer Care Center
- Forums
- Academy & Training
- Community Feedback & Updates
- Japan
- Anaplan Community Japan
- Anaplan Community Japan Knowledge Base
- HyperCare Japan
- JP-Central
- Support-Japanese
- Partners
- Partner Leadership Council
- Partner Product Council
- 724 Platform
- Anapedia
- App Hub
- Centers Of Excellence
- Extensions
- Planual
- Platform Updates
- 724 User Experience
- Profile Builder
- Resources
- Anaplan Advocates
- Anaplan Live!
- Community
- Community Advancement
- Community Connections
- Partner Program
- The Official Master Anaplanner Program
- Videos
- Welcome to the Anaplan Community!
- Success Central
- Support
- Case Portal Link
- Common Support Questions
- HyperCare Redirect
- Known Issues and Workarounds
- Support test page
- SupportFAQ
- Survey
- 2 Training Day Takeaways