I'm having some issues with the time settings on my L2 supply chain model, although it's only just starting to affect my work when I started on activity 2.3.9. 

 

For example, here is what my DEM03 module is showing, once I have all the formulas in:

sarabryn_0-1658855819339.png

I think this is coming from an issue in SYS01, which currently looks like this:

sarabryn_1-1658855926166.png

I'm pretty sure that more boxes should be checked than this. Is this an issue with the underlying data hub model, or did I miss something obvious?

Comments

  • sarabryn
    sarabryn Member, ALL USERS Posts: 4 Occasional Contributor

    Thanks, Jared!

  • sarabryn
    sarabryn Member, ALL USERS Posts: 4 Occasional Contributor

    Hi @JaredDolich , I'm several steps farther along in the sprint (I'm at 2.3.11.3). This is what I see when I try to save a line chart view of DEM03:

    sarabryn_0-1658929136926.png

    Is that what the initial demand forecast line is supposed to look like? My gut feeling is that there's an issue with the time scale somewhere, but every involved module I check is set to weeks.

     

  • sarabryn
    sarabryn Member, ALL USERS Posts: 4 Occasional Contributor

    Hi @JaredDolich,

     

    So sorry to be pulling this back up three weeks later! Even with the month filter on, I'm not seeing what you shared last:

    sarabryn_0-1660590324559.png

     

    Do you know where I might be going wrong with Baseline Forecast, Growth Rate, and Default Forecast? It looks like all three of those lines are stacked on top of each other. 

     