Level 2-Sprint 2 Import Historic data Action

Options
Diepcc
Diepcc Member, ALL USERS, Partner Posts: 4 New Contributor

Hi, I'm working on sprint 2, my model has successfully run action 9.1. the issue is that it's ignoring most of the data.

Can you tell me if this is ok or should I modify something on the action import source

Diepcc_0-1641863552142.png

 

Also attached is my Import structure

Diepcc_1-1641863601290.png


Diepcc_0-1641863779715.png

 

Best!

 

 

Comments

  • Diepcc
    Diepcc Member, ALL USERS, Partner Posts: 4 New Contributor

    Hi AntonMineev, thanks for taking the time.

     

    Here is a screenshot of the process:

    Diepcc_0-1641915320033.png

     

     

    Ok, I understand that part, but how may I correct this, so all the info is available to my supply chain model. 

  • Lintz
    Lintz Member, ALL USERS Posts: 1 New Contributor

    Displays the total points for all stories in the sprint. Story points are arbitrary measurements of the effort  not necessarily the time required to complete a story, based on the estimates of scrum team members. The default number in this field is zero - change the number to ensure that Completed points and Team points are calculated correctly.

     

    IndigoCard

  • Diepcc
    Diepcc Member, ALL USERS, Partner Posts: 4 New Contributor

    Hi  AntonMineev

     

    Thanks again for your help here is the screenshot 

     

    Diepcc_0-1642004486025.png

    Diepcc_1-1642004541301.png

    Diepcc_2-1642004575796.png

    Diepcc_3-1642004614306.png

    Diepcc_4-1642004633499.png

     

    Best