Break Circular Reference
Hi all,
I'm trying to set up a project planning model in Anaplan.
As part of this setup, I'm trying to calculate the start date and end dates based on the dependencies.
The logic I'm trying to build is as below,
Start Date = IF ISBLANK(Dependent Step) THEN Project Start Date + Lead Time ELSE End Date(LOOKUP: Dependent Step) + Duration
End Date = Start Date + Duration
But, if you see above there is a circular reference between Start Date and End Date.
Can someone please help me to break this circular reference or suggest any alternative for this.
Attached SS for your reference.
Comments
-
sgk6 Member, ALL USERS, Partner, Community Member, Certified Model Builder Posts: 5 Occasional Contributor
Hi @ManjunathKN , thanks for your response!
Could you please elaborate on how to use the LAG or Lead in this context as I'm not using the timescale dimension in this module.0 -
anikdas Member, ALL USERS, GroupMember, Master Anaplanner - Employee, Certified Master Anaplanner, Employee, Certified Model Builder Posts: 5 Master Anaplanner of the Year
Hi @sgk6 ,
As this is a time based circular reference, you will need to convert the steps by timescale first. In order to do that, create a module with project steps and time (day) as dimension. Then use a combination of lag to find out the actual start and end dates. Once done, bring back the results in the original module. Below are the screenshots and attached blueprints. One small thing - review the actual start date formula - when there is a dependent step, start date of next step should be end date of previous step + 1 and not end date of previous step + duration.
Hope this helps.
1
Categories
- All Categories
- 2.3K Anaplan Community
- Academy
- Anaplan Talent Builder
- Model Design Course
- The Anaplan Way
- Archive
- 2 Idea exchange
- 62 Enterprise Scale
- 1.1K Extensibility
- 21 Intelligence
- 1.6K Planning & Modeling
- 331 Security
- Community Connections
- Connections
- Experiences
- Groups
- Personas
- Employees
- CS Toolkit
- Customer Care Center
- Forums
- Academy & Training
- Community Feedback & Updates
- Japan
- Anaplan Community Japan
- Anaplan Community Japan Knowledge Base
- HyperCare Japan
- JP-Central
- Support-Japanese
- Partners
- Partner Leadership Council
- Partner Product Council
- 724 Platform
- Anapedia
- App Hub
- Centers Of Excellence
- Extensions
- Planual
- Platform Updates
- 724 User Experience
- Profile Builder
- Resources
- Anaplan Advocates
- Anaplan Live!
- Community
- Community Advancement
- Community Connections
- Partner Program
- The Official Master Anaplanner Program
- Videos
- Welcome to the Anaplan Community!
- Success Central
- Support
- Case Portal Link
- Common Support Questions
- HyperCare Redirect
- Known Issues and Workarounds
- Support test page
- SupportFAQ
- Survey
- 2 Training Day Takeaways