Level 2 Model Building

Options
Maggie
Maggie Member, ALL USERS, Community Member, Certified Model Builder Posts: 5 Occasional Contributor

Hi there,

 

For Sprint 3 of Level 2 model building activity (Build the product replenishment dashboard), I have forecast demand of 2,050 while Anaplan activity shows 2,005 as per the screenshots attached.

 

Thank you for your help.

Maggie 

Comments

  • Maggie
    Maggie Member, ALL USERS, Community Member, Certified Model Builder Posts: 5 Occasional Contributor

    @einas.ibrahim The only filter I have in DEM03 Demand Forecast module is to override 60 to 62 which made the forecast demand increase from 2048 to 2050. I remember in another activity the amount is showing as 2050 (in activity called Review the INV01 Line Item Formulas and Summary Method settings)Please see screenshots attached.

     

    Is it possible a typo in one of the activities?

     

    Thank you,

    Maggie